UPDATE: 6/2022
The weather slowed progress on exterior painting, but early May, initial interior painting and floors add more character to the rooms.
UPDATE: 6/2022
The construction site starts to look like a business with the exterior additions of landscaping and a paved parking lot.
UPDATE: 4/25/22
With sheetrock installed, the spaces have become more defined. It's starting to look like an actual hospital! These pictures show the treatment room, the lobby and the dental suites. For fun, compare with the previous photos on this page.
UPDATED 4/7/22
HVAC, electrical and plumbing are installed, though difficult to see in the pictures which show the lobby, the treatment area, and the dental suites.
UPDATED 3/17/2022
The interior space begins to take shape as framing gets started. In these photos, the lobby and treatment area are just starting to be defined. And the vaulted roof over the building entrance has been built.
UPDATED 12/2021
Check out the photos of the exterior walls going up!
UPDATED 12/2021
The competent BnK crew got an early start and the finished product looks great in the morning sunlight. The floor drains for the canine boarding area were delayed in shipping so that area will be poured soon. Stay tuned for the next step: time to go vertical.
UPDATED 11/2021
These photos show the outline for the foundation and one of the bioswales. There is a second bioswale on the opposite side of the lot. The bioswales will collect rain water, thus preventing rapid runoff into the street, and improving water quality.